Construction Progress Review Meeting #2

September 7, 2018

When: Saturday September 1, 2018

Where: New Masjid Construction Site

Time: 9:00 to 11:00 A.M

Minutes of Meeting/ Observations

Attendees:

ZCC: Brs. Ashraf Moton, & Zaheer Mohammed

CCC: Brs. Bashir Jangda, Shahem Barazi, Ajaz Lateef & Andy Shyahputra

All Good Builders: Br Hassan Al Ayoubi

New Items:

· Arches over windows need to be redone due to discrepancies

· Another Dumpster required on site

· Framing Crew is working on the site

· Stucco work in progress needs to be stopped till the mesh and Tyvek are

· inspected and approved.

· Offset to be provided for a vent pipe in the Men’s Washroom area to avoid

· interference with a window

· Height of 3 front doors to be made 10’-0” as per design

· South East & North East corners in front to be studied for closing the triangular

nook

· All Good Builders needs to concentrate on Framing & providing windows before

starting Stucco

· North West corner wall needs to be re-done with proper overlapping of Tyvek,

and mesh and get inspected before proceeding with Stucco

· All Good shall provide corner stone pieces at intersection of Stones & Stucco finishes

· The Roof Drainage system that was discussed with KJ Architects on August 31

was approved. The system consists of central high points on the roof with gutters

and downspouts on the side walls.

· Downspout colors to be suggested by KJ Architects and approved by CCC/ZCC

· Color schemes for the Stucco, Granite, Brick Veneer, doors & windows to be

suggested by KJ Architects & approved by CCC/ZCC

· All Good to submit change order request, for all items not covered in the

original contract, for approval prior to proceeding with the changes

· All Good to provide the correct framing for the Glass Door in the Main Hall on

the North West Area and for the steel door on the North East area near the stairs

Items from last meeting:

· The suspended ceiling in the front foyer would need to be provided at an elevation 1’-0” higher than that shown on the drawings to match the arches

· All Good to check the elevations of the framing of the parapet in the front

· All Good to get the rusted steel cleaned and apply primer coat

· All Good to check the riser near the Mehrab for possible use for Sprinkler

connection

· ZCC/ CCC will provide All Good with the revised floor and roof plans,

Gutter & Downspouts Details & Dome Details after receipt from KJ Architects

· All Good to provide 2 new windows on the Northern Wall at Second Floor

level. Size and type of windows to match the existing.

· All Good to provide samples of R-Panels, Stone & Granite to ZCC/CCC

for review and approval.

· ZCC/CCC to provide final color scheme to All Good after finalization with

KJ Architects

· All Good to provide new steel support for the door on the Northwest corner

Included are some pictures from the site meeting

 

 

Share on Facebook
Share on Twitter
Please reload

Featured Posts

BCIC December Events

1/1
Please reload

Recent Posts

December 2, 2018

Please reload

Archive
Please reload

Follow Us
  • Facebook Basic Square
  • Google Places Social Icon
ABOUT US

A welcoming community and center in the northwest of Houston service the Bear Creek, Copperfield and greater Cypress community, working together in the house of Allah to do the best for our community and make it a better place.

  • Grey Facebook Icon
  • Grey Google Places Icon
ADDRESS

17250 Coventry Park Dr.

Houston, TX 77084

STAY CONNECTED